Project Duration
Stipulated Date of Commencement
December 14 2012
Stipulated Date of Completion /
Likely Date of Completion January 12 2013
Likely Date of Completion January 12 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 823,021.00
Awarded for
₹ 926,207.80
Project highlights
Compound wall
Contractors
M/s. Sandeep R. S. Khandeparkar
Consultants
In-house (GSIDC)