Project Duration
Stipulated Date of Commencement February 15 2011
Actual Date of Completion August 16 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,150,885.00
Awarded for ₹ 17,177,265.00
Final Cost of Project ₹ 10,262,384.00

Project highlights

Construction of compound wall, motorised gate, railing, water fountain

 
Contractors
M/s. A. Ponnuraj
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
 

See Similar Projects

Stage lighting

View Project

Stage Lighting work

View Project

Fire Hydrant & Fire Alarm System.

View Project
x