Project Duration
Stipulated Date of Commencement June 16 2009
Actual Date of Completion November 30 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,783,602.00
Awarded for ₹ 7,994,225.00
 
Contractors
M/s. Hindustan Construction Corporation
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
 