Project Duration
Stipulated Date of Commencement
November 05 2008
Stipulated Date of Completion /
Likely Date of Completion January 04 2009
Likely Date of Completion January 04 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 599,437.00
Awarded for
₹ 920,420.90
Project highlights
Construction of retaining wall and drainage, laterite masonry parapets & concrete road
Contractors
M/s. C.H. Abdullah
Consultants
In-house (GSIDC)