Project Duration
Stipulated Date of Commencement
November 05 2008
Actual Date of Completion
January 04 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 599,437.00
Awarded for
₹ 920,420.90
Final Cost of Project
₹ 455,178.00
Project highlights
Construction of retaining wall and drainage, laterite masonry parapets & concrete road
Contractors
M/s. C.H. Abdullah, M/s. C.H. Abdullah
Consultants
Inhouse, Inhouse