Project Duration
Stipulated Date of Commencement January 15 2015
Stipulated Date of Completion /
Likely Date of Completion
July 14 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ Rs. 2,38,59,753.00
Awarded for ₹ 27,299,749.39

Project highlights

Construction of 10 cattle sheds

 
Gallery Image
Contractors
M/s. Bharti Infrastructure Developers
Gallery Image
Consultants
M/s. Creative Abode
 
Similar Projects

See Similar Projects

Similar Project

Construction of Yojana Bhavan for Directorate of Planning, Statistics and Evaluation at Porvorim, Goa

View Project
Similar Project

Supply, installation, testing & commissioning of C1287 RMU

View Project
Similar Project

Painting Landscaping and other ancillary works along DB Road for IFFI 2017 : SH Fencing & railing work along DB Road

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.