Project Duration
Stipulated Date of Commencement
May 26 2013
Stipulated Date of Completion /
Likely Date of Completion September 25 2013
Likely Date of Completion September 25 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,940,400.00
Awarded for
₹ 15,969,460.00
Project highlights
The work includes landscaping, laying pavers etc.
Contractors
M/s. Sandeep R. S. Khandeparkar
Consultants
M/s. Frischmann Prabhu (India) Pvt. Ltd.