Project Duration
Stipulated Date of Commencement
May 12 2010
Stipulated Date of Completion /
Likely Date of Completion January 11 2011
Likely Date of Completion January 11 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 46,672,500.00
Awarded for
₹ 38,840,799.45
Project highlights
Landscape & beautification of Ralloitollem lade area.
Contractors
M/s. Ultracon Constructions Pvt. Ltd.
Consultants
M/s. Effective Architectural Services