Project Duration
Stipulated Date of Commencement March 24 2012
Actual Date of Completion March 23 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 49,542,943.00
Awarded for ₹ 57,814,020.00
Final Cost of Project ₹ 36,474,896.00

Project highlights

Providing and fixing of pavers and kerbstones for footpaths, benches, cast iron lamp posts,repairs to storm water drains with covered precast RCC slabs and landscaping at various location in the jurisdiction of VP Azossim Mandur and VP Neura

 
Contractors
M/s Shilpi Constructions
Consultants
M/s. Nitin Arolkar
 

See Similar Projects

Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa -HVAC work

View Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – SH: Reprogramming of Audio Video System installed at Sub-District Hospital, Ponda – Goa.

View Project

Providing 11 kV transformer substation for release of electrical connection to the office premises of Commercial Tax Office at Vasco.

View Project
x