Project Duration
Stipulated Date of Commencement
March 24 2012
Stipulated Date of Completion /
Likely Date of Completion March 24 2013
Likely Date of Completion March 24 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,542,943.00
Awarded for
₹ 57,814,020.00
Project highlights
Providing and fixing of pavers and kerbstones for footpaths, benches, cast iron lamp posts,repairs to storm water drains with covered precast RCC slabs and landscaping at various locations in the jurisdiction of VP Azossim Mandur and VP Neura
Contractors
M/s.Shilpi Constructions
Consultants
M/s. Nitin Arolkar