Project Duration
Stipulated Date of Commencement
July 19 2016
Stipulated Date of Completion /
Likely Date of Completion September 01 2016
Likely Date of Completion September 01 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,690,434.00
Awarded for
₹ 56,98,678.15
Project highlights
Alllied construction works such as roofing and hall at GHS Ambaulim.
Contractors
M/s. K. G. Thomas
Consultants
Creative Abode