Project Duration
Stipulated Date of Commencement
July 19 2016
Actual Date of Completion
December 22 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,690,434.00
Awarded for
₹ 56,98,678.15
Final Cost of Project
₹ 5,530,253.00
Project highlights
Alllied construction works such as roofing and hall at GHS Ambaulim.
Contractors
M/s. K.G.Thomas, M/S. K G THOMAS, M/S. K G THOMAS
Consultants
Creative Abode