प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख
April 23 2016
पुराय जावपाची प्रत्यक्ष तारीख
April 05 2022
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च
₹ 236,470,437.00
दिले
₹ 242,441,097.11
प्रकल्प हायलायट्स
Cfonstruction of 2 Lane Bridge with approaches.

कंत्राटदार
M/s. Larsen & Toubro Ltd.

सल्लागार
M/s. Rahul Deshpande
उप-काम
ह्या प्रकल्पांत 2 उप-कामांचो आसपाव आसा. हाचो तपशील सकयल उपलब्ध आसा.
1
Construction of Bridge across Rua de Ourem Creek, Panaji – Shifting of 11 KV Cable
100% पुराय जाल्ले
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख
November 29 2017
पुराय जावपाची प्रत्यक्ष तारीख
December 02 2017
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च
₹ 253,495.00
दिले
₹ 276,450.00
प्रकल्प हायलायट्स
The scope of work includes supply, installation, testing & commissioning of 11 KV, 3C x 300 sq. mm, underground armored cable – 120 meters length.

कंत्राटदार
M/s. Pristine Engineering Services

सल्लागार
M/s. Rahul Deshpande
2
Construction of Bridge across Rua de Ourem Creek, Panaji – Shifting of 33 kV Overhead Lines
100% पुराय जाल्ले
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख
January 17 2018
पुराय जावपाची प्रत्यक्ष तारीख
March 26 2018
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च
₹ 571,048.00
दिले
₹ 597,920.00
प्रकल्प हायलायट्स
The scope of work includes dismantling of existing 33kV overhead lines and installation, testing & commissioning of 33 KV, 3C x 400 sq. mm, underground armored cable supplied by Goa Electricity Department.

कंत्राटदार
M/s. Pristine Engineering Services

सल्लागार
M/s. Rahul Deshpande

अशेच तरेचे प्रकल्प पळोवचे

Hotmiixing of road in Fatorda for Lusofonia Games
तपशील पळोवचे
Widening of roads and relocation of structures in Fatorda Constituency – Phase II – Illumination of Footpath from Colva Circle to Ravindra Bhavan Circle at Fatorda, Margao, Goa
तपशील पळोवचे
Phase II
तपशील पळोवचे