Project Duration
Stipulated Date of Commencement November 30 2019
Stipulated Date of Completion /
Likely Date of Completion
July 29 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 14,689,939.00
Awarded for ₹ 11,974,787.00

Project highlights

furniture work

 
Gallery Image
Contractors
M/s. Infiniti Modules Pvt. Ltd.,
Gallery Image
Consultants
M/s.Banaji & Associates
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Dharbandora Taluka – Package IV (GPS Hauliwada, GPS Kalsai, GPS Camarconda, GPS Matoje, GPS Panaswada)

View Project
Similar Project

Upgradation/Renovation of Government College at Quepem, Goa -Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.

View Project
Similar Project

Repairs/Upgradation & maintenance of Government SchoolS in State of Goa – Civil, Plumbing & Electrical works – Package B (Quepem Taluka) – GPS Borimal, GPS Gajanan, GPS Chinchnagar, GPS Kamral, GPS Kumbharwada Sirvoi

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.