Project Duration
Stipulated Date of Commencement June 19 2024
Stipulated Date of Completion /
Likely Date of Completion
September 18 2024
Status
0%
Completed
Cost (₹)
Estimated at ₹ 4,317,391.53
Awarded for ₹ 4,520,748.60

Project highlights

Supply, Installation, Testing and Commissioning of DG Set.

 
Gallery Image
Contractors
M/s. Imperial Engineering Company
Gallery Image
Consultants
M/s. FP Project Management
 
Similar Projects

See Similar Projects

Similar Project

Construction of New Hospital Block in place of existing Hospital for Institute of Psychiatry & Human Behaviour, Goa : Substation and allied works – Electrical

View Project
Similar Project

Construction of New Premises for Community Health Centre at Tuem, Pernem, Goa: Balance Civil & Plumbing works.

View Project
Similar Project

Balance Fire-fighting works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.