Project Duration
Stipulated Date of Commencement
February 18 2024
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
19%
Completed
Cost (₹)
Estimated at
₹ 7,252,638.47
Awarded for
₹ 7,816,121.71
Project highlights
Fire-fighting, fire alarm and fire supression system of the building.
Contractors
M/s. Antifire Systems
Consultants
M/s. KICONS Limited