Project Duration
Stipulated Date of Commencement October 17 2021
Stipulated Date of Completion /
Likely Date of Completion
January 16 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,241,960.89
Awarded for ₹ 25,063,416.99

Project highlights

Demolition & Re-construction work.
Ground floor – Bank, Panchayat office, Health.
First floor – Multipurpose Hall.

 
Gallery Image
Contractors
M/s. V. Construct
Gallery Image
Consultants
M/S. Gurudutt Sanzgiri
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing and Commissioning of street light poles and fixtures along with allied electrical works for the stretch from Odxel junction to GMC

View Project
Similar Project

Lift/ Elevator Work

View Project
Similar Project

Renovation of Rajiv Gandhi Kala Mandir at Ponda.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.