Project Duration
Stipulated Date of Commencement
October 05 2007
Stipulated Date of Completion /
Likely Date of Completion October 04 2008
Likely Date of Completion October 04 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 37,518,970.00
Awarded for
₹ 44,608,744.20
Contractors
M/s. M. M. Naik & Co.
Consultants
M/s. Vijaykumar Sawant Associates