Project Duration
Stipulated Date of Commencement November 13 2017
Stipulated Date of Completion /
Likely Date of Completion
November 12 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 127,693,445.00
Awarded for ₹ 133,860,915.16

Project highlights

Olympic size Swimming Pool of size 50x25x2m.
Diving Pool of size 18x18x4.5m with RCC diving platforms for heights 1m. 3m. 5m & 7.5m.
Kids Pool of 150M2, Filtration Plant -200 m2.

 
Gallery Image
Contractors
M/s. S.N. Construction
Gallery Image
Consultants
M/s TPF Engineering Pvt. Ltd. (Goa Regional Office)
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Dharbandora Taluka – Package III (GPS Phalaskta, GPS Molem, GPS Jambolim, GPS Kasavali, GPS Bordumol)

View Project
Similar Project

Re-construction of GPS at Vithalapur in Sankhali, Bicholim Taluka.

View Project
Similar Project

Interiors and Furniture work.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.