Project Duration
Stipulated Date of Commencement
July 10 2004
Stipulated Date of Completion /
Likely Date of Completion October 15 2004
Likely Date of Completion October 15 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 76,400,000.00
Awarded for
₹ 40,155,000.00
Project highlights
Supply of cables
Contractors
M/s. Electro Engineering Enterprises
Consultants
M/s. TPF Engineering Pvt. Ltd
See Similar Projects
Collecting and segregating solid waste material strewn on eiher sides of National Highway NH-17, NH-17A and NH-17B within Goa, transportation and storing at designated locations.
View Project
Supply and laying of 33KV HT cable from Sai service junction to the new High Court Complex and allied electrical works
View Project
Replacement of failed cables and supply, installation of new fixtures, spares for the streetlights along D.B. Marg from Kadamba Bus stand to Miramar Circle (IFFI 2018)
View Project