Project Duration
Stipulated Date of Commencement December 14 2013
Stipulated Date of Completion /
Likely Date of Completion
February 11 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,256,625.00
Awarded for ₹ 5,005,711.00
 
Gallery Image
Contractors
M/s. Godrej & Boyce Mfg. Co. Ltd.
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 