Project Duration
Stipulated Date of Commencement
December 15 2006
Stipulated Date of Completion /
Likely Date of Completion September 14 2007
Likely Date of Completion September 14 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 36,821,547.83
Awarded for
₹ 44,928,213.47
Project highlights
Hard landscaping includes upgradation of existing road networks, adequate pedestrian walkways, construction of planters, and basic infrastructural items like storm water drainage, irrigation system, erection of gates and other civil works related to landscape design.
Contractors
M/s. My Associates
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Civil & Plumbing works (Phase-II) – Balance works.
View Project
Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for the Lecture Hall Elevator and Girls Hostel Elevator installed at Goa Medical College and Hospital, Bambolim for three years (2018-2021).
View Project
Construction of Primary Health Centre at Navelim, Margao, Goa.
View Project