Project Duration
Stipulated Date of Commencement
July 24 2018
Stipulated Date of Completion /
Likely Date of Completion June 07 2019
Likely Date of Completion June 07 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,926,443.00
Awarded for
₹ 8,860,021.10
Project highlights
Repairs/Renovation works
Contractors
M/s. Savita Developers & traders
Consultants
M/S. Bhaskar wagle & associates