Project Duration
Stipulated Date of Commencement
May 03 2018
Stipulated Date of Completion /
Likely Date of Completion March 16 2019
Likely Date of Completion March 16 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 18,154,203.78
Awarded for
₹ 18,722,224.15
Project highlights
Repairs/Upgradation & maintenance of Government Schools
Contractors
M/s. K. G. Thomas
Consultants
M/s. Creative Abode
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing,Electrical works – Packge XII- Mormugao Taluka
View Project
Repairs/Upgradation and Maintenance of Government Schools in the State of Goa – Civil, Plumbing and Electrical works in :-Bardez Taluka – GPS Carambolim.
View Project
Construction of Government High School at Bhuipal in Sattari Taluka.
View Project





