Project Duration
Stipulated Date of Commencement
June 29 2018
Stipulated Date of Completion /
Likely Date of Completion January 08 2019
Likely Date of Completion January 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,490,150.00
Awarded for
₹ 8,107,253.90
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s.Nilambari Constructions
Consultants
M/s.Allwyn Crasto