Project Duration
Stipulated Date of Commencement
November 08 2016
Stipulated Date of Completion /
Likely Date of Completion October 04 2017
Likely Date of Completion October 04 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 22,020,515.00
Awarded for
₹ 25,758,385.53
Project highlights
Construction of New Modern School building
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Bhasker Wagle & Associates