Project Duration
Stipulated Date of Commencement
September 18 2019
Stipulated Date of Completion /
Likely Date of Completion March 03 2019
Likely Date of Completion March 03 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,755,042.00
Awarded for
₹ 7,558,715.77
Project highlights
Repairs of Govt. Schools in Pernem Taluka – Civil, Plumbing, Electrical works
Contractors
M/s. Race Constructions
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
Repairs/Upgradation and maintenance of Government Schools in the state of Goa – Package VIA (Salcete Taluka)
View Project
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works in Bicholim Taluka- Package A-(G.P.S. Kahtar Dabdaba, G.P.S. Lamgao, G.P.S. Bagwada Pilgao, G.P.S. Mathwada Pilgao)
View Project
Repairs/ Upgradation & Maintenance of Government schools in the State of Goa –Civil, Plumbing & Electrical works in Bardez Taluka :- GPS Betim, GPS Salvaor do Mund, GPS Paithona
View Project