Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion February 21 2015
Likely Date of Completion February 21 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,708,909.00
Awarded for
₹ 24,912,755.00
Project highlights
Repair & reconstruction of the school building block
Contractors
M/s. MM Naik
Consultants
M/s. Prakash Lawande Associate