Project Duration
Stipulated Date of Commencement
August 01 2018
Stipulated Date of Completion /
Likely Date of Completion April 15 2019
Likely Date of Completion April 15 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,558,643.00
Awarded for
₹ 9,059,511.97
Contractors
M/s. Savita Developers & traders
Consultants
M/s. Vaishali Pednekar Associates