Project Duration
Stipulated Date of Commencement
January 03 2015
Stipulated Date of Completion /
Likely Date of Completion August 31 2015
Likely Date of Completion August 31 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,000,000.00
Awarded for
₹ 20,000,000.00
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Bhasker Wagle & Associates