Project Duration
Stipulated Date of Commencement September 20 2017
Stipulated Date of Completion /
Likely Date of Completion
September 19 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 50,00,000.00
Awarded for ₹ 59,42,392.51

Project highlights

Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.

 
Gallery Image
Contractors
M/s. S M Realtors
Gallery Image
Consultants
M/s. Vaishali Pednekar Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Government Primary School, Toncawada, Jua, St. Estevam in Tiswadi Taluka.

View Project
Similar Project

Repairs/Upgradation and Maintenance of Government Schools in the State of Goa – Civil, Plumbing, Electrical works – Package VI- (Ponda Taluka)

View Project
Similar Project

Construction of Government Primary School at Shantinagar – Pissurlem in Sattari Taluka.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.