Project Duration
Stipulated Date of Commencement
January 18 2019
Stipulated Date of Completion /
Likely Date of Completion September 27 2019
Likely Date of Completion September 27 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,770,090.00
Awarded for
₹ 8,544,274.32
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
Repairs and upgradation of Govt. High School in the State of Goa- Pernem Taluka- Package A
View Project
Repairs/Upgradation & maintenance of Government schools in the state of Goa – Civil, Plumbing & Electrical works- Package-IV (Sattari Taluka )
View Project
Repairs/Upgradation and Maintenance of Government Schools in the State of Goa – Civil, Plumbing and Electrical works in :-Bardez Taluka – GPS Carambolim.
View Project





