Project Duration
Stipulated Date of Commencement
February 28 2015
Stipulated Date of Completion /
Likely Date of Completion August 28 2015
Likely Date of Completion August 28 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 18,737,089.00
Awarded for
₹ 22,589,546.91
Project highlights
Repairs of Busstand
Contractors
M/s. Race Construction
Consultants
M/s. Bhasker Wagle & Associates