Project Duration
Stipulated Date of Commencement
October 31 2019
Stipulated Date of Completion /
Likely Date of Completion November 14 2020
Likely Date of Completion November 14 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,311,608.00
Awarded for
₹ 11,745,339.03
Project highlights
Repairs/Renovation works
Contractors
M/s. A. Y. Gulumkar
Consultants
M/s. Manoj M. Amshekar