Project Duration
Stipulated Date of Commencement July 29 2017
Stipulated Date of Completion /
Likely Date of Completion
July 28 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,49,30,773.00.
Awarded for ₹ .3,38,09,091.00.00

Project highlights

The renovated office premises of Excise Station, involves repair of ground and Mezzanine Floor. Parking provision is also provided for 6nos (four wheelers) and 12nos (two wheelers). The project methodology involves adaptive reuse of this heritage structure including.
a) Major civil repairs to existing structure.
b) Reconstruction of the collapsed part of the existing structure.
c) Structural retrofit to conform to standard building codes.
d) Upgradation of existing facilities including Civil and Mechanical, Electrical & Plumbing (MEP) works to conform to higher standard of usability.
e) Interior refurbishment to facilitate efficient usage.
Repair of office premises for Excise Department. The renovated office premises of Excise Station, involves repair of ground and Mezzanine Floor. Parking provision is also provided for 6nos (four wheelers) and 12nos (two wheelers). The project methodology involves adaptive reuse of this heritage structure including.

 
Gallery Image
Contractors
M/s.Kishore K. Shah Engineers & Contractor
Gallery Image
Consultants
M/s.Pankaj Joshi Consultants
 
Similar Projects

See Similar Projects

Similar Project

Refurbishment of Maquinez Palace, Maquinez Palace Annexe, Heritage Building (ESG), Panaji, Goa – Civil, Plumbing & Electrical works.

View Project
Similar Project

Construction of new building for SCERT at Porvorim, Goa

View Project
Similar Project

Renovation of office premisies of Regional Employment Exchange, Panaji

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.