Project Duration
Stipulated Date of Commencement August 20 2014
Stipulated Date of Completion /
Likely Date of Completion
November 19 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 60,002,811.80
Awarded for ₹ 54,000,000.00

Project highlights

Temporary office premises for GSIDC office and the District & Sessions Court untill the permanent premises is ready to be occupied.

 
Gallery Image
Contractors
M/s. Knchan Associates,
Gallery Image
Consultants
M/s. Ameet Sukhthankar Architect,
 
Similar Projects

See Similar Projects

Similar Project

Providing 11 kV transformer substation for release of electrical connection to the office premises of at Vasco.

View Project
Similar Project

Construction of seed processing and storage unit building at Ella, Old Goa.

View Project
Similar Project

Fire suppression system.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.