Project Duration
Stipulated Date of Commencement
February 27 2004
Stipulated Date of Completion /
Likely Date of Completion December 25 2004
Likely Date of Completion December 25 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 39.85 lakh
Awarded for
₹ 39.81 lakh
Contractors
M/s. Sandesh C. Naik and M/s. C. V. Naik & Son
Consultants
M/s. Vijaykumar Sawant Associates