Project Duration
Stipulated Date of Commencement
November 23 2017
Stipulated Date of Completion /
Likely Date of Completion November 22 2020
Likely Date of Completion November 22 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,536,750.00
Awarded for
₹ 1,399,200.00
Project highlights
Maintenance of Cold storages in Goa Medical College
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd
Consultants
In-house (GSIDC)