Project Duration
Stipulated Date of Commencement
October 14 2008
Stipulated Date of Completion /
Likely Date of Completion December 29 2008
Likely Date of Completion December 29 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,000,480.00
Awarded for
₹ 1,847,925.00
Contractors
M/s.James Electricals
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.