Project Duration
Stipulated Date of Commencement
March 25 2021
Stipulated Date of Completion /
Likely Date of Completion April 08 2021
Likely Date of Completion April 08 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,062.00
Awarded for
₹ 52,465.00
Project highlights
The scope of work includes Supply, Installation, Testing & Commissioning of 200 A Distribution BOX. for obtaining electricity connection to PHC Navelim.
Contractors
M/s. Consistent Engineers
Consultants
In-house (GSIDC)