Project Duration
Stipulated Date of Commencement
June 29 2017
Stipulated Date of Completion /
Likely Date of Completion February 28 2018
Likely Date of Completion February 28 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,40,35,435.00
Awarded for
₹ 1,49,08,082.49
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Creative Abode
See Similar Projects
Construction of Hostel at Government College of Arts, Science & Commerce at Sanquelim, Goa – Balance work
View Project
Repairs/Upgradation of Government High School at Vadenagar,Vasco, Goa.
View Project
Repairs & Upgradation of Government Higher Secondary School Sanquelim.
View Project