Project Duration
Stipulated Date of Commencement
December 28 2010
Stipulated Date of Completion /
Likely Date of Completion March 28 2011
Likely Date of Completion March 28 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,166,556.00
Awarded for
₹ 6632510.73
Contractors
M/s. M. M. Naik & Co.
Consultants
M/s. Datta Kare Associates