Project Duration
Stipulated Date of Commencement
August 03 2015
Stipulated Date of Completion /
Likely Date of Completion January 02 2016
Likely Date of Completion January 02 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,138,334.44
Awarded for
₹ 16,700,040.00
Project highlights
painting of schools, flooring, roofing, structural repairs etc.
Contractors
M/s. Shivam Infratech
Consultants
M/s. Creative Abode