Project Duration
Stipulated Date of Commencement
January 22 2019
Stipulated Date of Completion /
Likely Date of Completion September 21 2019
Likely Date of Completion September 21 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,216,332.00
Awarded for
₹ 11,323,121.33
Project highlights
Repairs, Upgradation & Maintenance work, civil, plumbing, Electrical etc.
Contractors
M/s.M kumar homes
Consultants
M/S. Creative Adobe