Project Duration
Stipulated Date of Commencement November 06 2019
Stipulated Date of Completion /
Likely Date of Completion
October 09 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,361,697.34
Awarded for ₹ 3,014,078.00
 
Gallery Image
Contractors
M/s. Raveena Watertech
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Electrical Works.

View Project
Similar Project

Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Supply, Installation, Testing & Commissioning of Cold storage unit for Microbiology Department at Goa Medical College.

View Project
Similar Project

Supply of Syringe pumps

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.