Project Duration
Stipulated Date of Commencement
May 26 2013
Stipulated Date of Completion /
Likely Date of Completion November 25 2013
Likely Date of Completion November 25 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,50,771.00
Awarded for
₹ 23,88,737.00
Contractors
M/s. Mohan Electricals
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Supply, Installation, Testing and Commissioning of Cautery Machine
View Project
Supply Installation Testing & Commissioning of Hospital Furniture.
View Project
Procurement of Equipment for the Burns Unit (New Ward 118), Department of Plastic Surgery, Goa Medical College, Bambolim –Goa- SH-Supply, Installation, Testing and Commissioning of Defibrillator with Monitor
View Project





