Project Duration
Stipulated Date of Commencement August 05 2019
Stipulated Date of Completion /
Likely Date of Completion
August 04 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 136,000.00
Awarded for ₹ 136,000.00

Project highlights

Maintenance of UPS systems at Sub-District Hospital, Chicalim

 
Gallery Image
Contractors
M/s. Renutron,
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Demolition and construction of hospital and hostel at Mandur, Goa

View Project
Similar Project

Supply and Installation of Office Furniture

View Project
Similar Project

Supply, Installation, Testing and Commissioning of ACT machine

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.