Project Duration
Stipulated Date of Commencement September 17 2023
Stipulated Date of Completion /
Likely Date of Completion
January 15 2024
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,363,408.00
Awarded for ₹ 1,488,131.00

Project highlights

Supply, installation, testing and commissioning of UPS.

 
Gallery Image
Contractors
M/s. Powertrac Corporation
Gallery Image
Consultants
M/s. Frischmann Prabhu I Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of NICU at Goa Medical College, Bambolim-Goa – Office Furniture

View Project
Similar Project

Updating the work of provision of fire safety measures at Goa Medical College and Goa Dental College, Bambolim, Goa.

View Project
Similar Project

Supply, Installation, Testing and Commissioning of Temporary pace makers

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.