Project Duration
Stipulated Date of Commencement
July 26 2019
Stipulated Date of Completion /
Likely Date of Completion July 25 2022
Likely Date of Completion July 25 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,110,000.00
Awarded for
₹ 1,110,000.00
Project highlights
Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa
Contractors
M/s.Dubas Engineering Pvt. Ltd
Consultants
In-house (GSIDC)