Status
Completed
Contractors
Consultants
Sub Works
This project involved 2 sub works. The details of the same available below
1
Civil, Plumbing & Electrical works.
100% completed
Project Duration
Stipulated Date of Commencement
December 27 2013
Stipulated Date of Completion /
Likely Date of Completion January 08 2015
Likely Date of Completion January 08 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 73,214,248.00
Awarded for
₹ 85,526,271.00
Contractors
M/s. R. B. S. Candiaparcar
Consultants
M/s. Datta Kare Associates
2
Furniture work.
100% completed
Project Duration
Stipulated Date of Commencement
February 27 2015
Stipulated Date of Completion /
Likely Date of Completion April 26 2015
Likely Date of Completion April 26 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,323,598.00
Awarded for
₹ 6,353,797.50
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
M/s. Datta Kare Associates
See Similar Projects
Construction of Government Primary School, Toncawada, Jua, St. Estevam in Tiswadi Taluka.
View Project
Construction of new Government Primary and Secondary Schools in the State of Goa – GHS at Honda, GPS at Bhironda and GHS at Guleli in Sattari taluka.
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Pernem Taluka: Package-III (GPS Vithaladevi, GMS Paraskade, GPS Oshalbaag) – 5th Call
View Project