Project Duration
Stipulated Date of Commencement
February 18 2019
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
93%
Completed
Cost (₹)
Estimated at
₹ 37,809,607.00
Awarded for
₹ 33,622,376.30
Project highlights
Total area of the premises – 976 sq.m – 2 floors. 3rd floor – Cabins for ACCT, ACTO, CTO and other office space, server room, toilets, pantry. 4th Floor -Cabins for ACCT, ACTO, CTO and other office space, multipurpose hall, compactors room, server room, pantry, toilets, conference room
Contractors
M/s. Knchan Associates
Consultants
M/s. Ameet Sukhthankar