Project Duration
Stipulated Date of Commencement
January 06 2023
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
95%
Completed
Cost (₹)
Estimated at
₹ 8,836,280.00
Awarded for
₹ 9,116,708.25
Project highlights
External Development work consisting of Construction of retaining wall, levelling, Construction of compound wall, erection of signages, laying of paver, railing etc
Contractors
M/s K G Thomas
Consultants
Ms Murty & Manyam